Fiber Final Design Review Passed

The Final Design Review of the Fiber work package led by IAC has been held on November 22nd. This review was a success review leading to minor adjustments.

The procurement process can now start in parallel with the manufacturing of several mechanical parts. The complete package is planned to be delivered to Geneva in les than one year now (Oct 2018). Octogonal and rectangular fiber, already ordered, are scheduled to arrive in December at IAC.

The NIRPS Fiber WP schematics   The Invar prototype of the output end (cryo) of the Fiber WP